Hydro-Québec is proud to announce the commissioning of the first of two generating units at Romaine-1 generating station. As of November 25, Hydro-Québec’s generating fleet can rely on an additional 135 MW of power. Commissioning of the second unit is scheduled for the end of 2015.
With winter just around the corner, this new capacity arrives in time to help meet Québec’s demand during winter peaks. It will also enable Hydro-Québec to take advantage of profitable business opportunities on the export market.
A world first
Begun in April 2012, the Romaine-1 worksite was the set of a world first, with the assembly of the first generating unit executed in under 12 months, a task usually requiring 14 to 16 months. In addition, all of the structures were built in 42 months, rather than 49 months, which is seven months ahead of schedule.
Hydro-Québec would like to highlight the remarkable work accomplished by its employees, workers, and contractors who made it possible to commission the units
Economic spinoffs and jobs
Over 2,000 workers were active on the Romaine hydroelectric complex jobsite at the project’s peak in 2015, for a fourth consecutive year. Since the beginning of the project, some 45% of workers were from the Côte-Nord region.
To date, work on the Romaine jobsite has generated contracts worth over $3 billion, including nearly $800 million awarded to companies in the Côte-Nord.
Work continues
Romaine-1 is the second generating station of the Romaine complex to be put in service over the past 12 months. The first generating station of the complex, Romaine-2, was commissioned at the end of 2014.
Work forges ahead at the Romaine-3 jobsite, with commissioning scheduled for the end of 2017. In 2016, work will begin on the fourth and final structure of the complex, namely the construction of Romaine-4, scheduled for commissioning in 2020.
Marie-Elaine Deveault
Press Officer
Hydro-Québec
July 16, 2025, General news
Hydro-Québec to expand its no-cost smart thermostat program to water heaters
July 10, 2025, General news
Hydro-Québec – Issue of Debentures Due February 15, 2065 on the Canadian Market
July 8, 2025, General news
Future hydroelectric development on Gull Island – Hydro-Québec begins preliminary field studies