Hydro-Québec, January 5, 2018 — From January 5 to 9, 1998, southern Québec was coated in up to 110 millimeters of ice, plunging more than three million people into the dark. Even though Hydro-Québec’s system was three times stronger than the standards required at the time, it caved in. Since then, Hydro-Québec has made significant improvements to its system throughout Québec, resulting in a more robust and reliable network, able to stand fast in all kinds of weather conditions.
Under the weight of the ice that fell in January 1998, 1,500 towers were damaged. At the height of the crisis, nearly 1.4 million Québec households were without electricity, and more than three million Quebecers went without power for several days.
Up to 10,000 people were hard at work to restore electricity to the several regions affected by this unprecedented storm. With all hands on deck, our employees also counted on the help of workers from neighboring electric utilities, Sécurité civile du Québec representatives, Canadian Armed Forces soldiers, and subcontractors.
Unfazed by working 12–16 hour days, in just two weeks, they managed to build a temporary high-voltage transmission line to supply power to the Greater Montréal area. This was a truly impressive feat, as such an operation would normally require three to four months of work. The last customer was finally reconnected a month after the ice storm began.
To learn more about what happened, visit our new virtual exhibition, Icy January: http://www.hydroquebec.com/ice-storm-1998
Damage done, lessons learned
At the time of the storm, Hydro-Québec’s equipment met Government of Canada standards, designed to withstand ice storms three times as severe as what was required Still, it wasn’t able to shoulder the brunt of the storm, and Hydro-Québec has since reinforced its equipment and system to prevent such a crisis in the future.
For example, over than 900 km of lines have been rebuilt using much more stringent design criteria. The new 735-kV Chamouchouane–Judith-Jasmin transmission line is part of the strategy to better supply the greater Montréal area. The company can now also rely on the Sygivre system, a sensor that triggers an alert if icing accumulates on power lines.
It is hard to predict whether a storm of such magnitude will ever happen again. But if it did, we’ll be better equipped to face it. Our system is decidedly more reliable and more solid, and our employees have shown that, in times of crisis, they don’t think twice about rolling up their sleeves to serve our customers.
The 1998 ice storm in numbers:
A more reliable, robust system
In pictures (click for high-resolution version) :
-30-
Media team - Hydro - Québec
April 2, 2026, General news
Hydro-Québec announces new grant to accelerate solar self-generation
March 27, 2026, Montréal
Hydro-Québec to reinforce the grid and increase capacity at Saint-Jean substation
March 25, 2026, General news
Hydro-Québec launches Request for Information to inform potential development of offshore wind farms off Nova Scotia